Problem

A duplex wastewater lift station shows intermittent high-level alarms, longer-than-normal pump run times, and inconsistent drawdown even though lead-lag alternation appears to be functioning.

Assessment

RMS starts by checking the station as a complete operating system, comparing wet-well behavior, lead-lag sequencing, operating current, available discharge observations, check-valve behavior, accessible piping condition, and pump response during drawdown.

Service Scope

  • Confirm wet-well level behavior and lead-lag sequencing
  • Record operating current and available discharge observations
  • Remove, clean, and inspect the affected pump
  • Review check-valve behavior and accessible discharge components
  • Verify rotation, current draw, sequencing, and drawdown after reinstallation

Technical Details

  • Duplex wastewater lift station operating behavior
  • Wet-well drawdown and high-level alarm response
  • Lead-lag sequencing, operating current, and check-valve observations
  • Pump removal, cleaning, inspection, and reinstallation support

Return-to-Service Standard

The return-to-service target is predictable drawdown, normal sequencing, and documented observations that help operators recognize future changes before they become emergency calls.